Ontario Postpones Commencement of Excess Soil Regulation
The Province of Ontario recently announced that the implementation of the new Excess Soil Regulation, O. Reg 406/19: On-Site and Excess Soil Management (O. Reg 406/19), would be delayed as a result of the COVID-19 pandemic. O. Reg 406/19 will be implemented in three phases. The first phase only will be delayed by six months to January 1, 2021 to allow the construction industry to prioritize their response to the COVID-19 pandemic. This delay will also provide the construction industry with additional time to adjust to the new regime of excess soil management.
Regulation of Excess Soils
In December 2019, the Province of Ontario enacted O. Reg 406/19. This regulation provides a complete code for the movement of soils between two or more properties, which was previously subject to a patchwork of municipal and provincial regulation.
Under O. Reg 406/19, soils excavated as part of a project that are to be moved off-site, known as excess soils, are deemed to be a “waste” and cannot be re-used, except as specified in the regulation. In particular, excess soils can be transported and re-used at a site if the site owner consents to the transfer, the soil remains sufficiently dry, and the re-use site is subject to an enumerated instrument, such as a site alteration permit or certificate of property use. Excess soils must be excavated, stored, and deposited in accordance with O. Reg 406/19, which includes specific requirements to ensure that excess soils do not contain contamination exceeding applicable provincial standards. Finally, all transportation of excess soils must be tracked, documented, and filed with the Province in a similar manner to hazardous wastes governed under Regulation 347: General Waste Management.
Currently, O. Reg 406/19 is not in force. The provincial government initially proposed that O. Reg 406/19 would be brought into force in three phases on the dates set out below:
- First phase: July 1, 2020 for the standards governing the re-use of excess soils, the processing of excess soils at project areas, and transportation of excess soils;
- Second phase: January 1, 2022 for the standards governing all documentation, tracking, and filing requirements associated with the removal of excess soils from a project area, as well as the operation of re-use sites; and
- Third phase: January 1, 2025 for the prohibition against depositing excess soil at landfilling sites.
Delay of First Phase
On June 12, 2020, the provincial government enacted O. Reg 270/20: On-Site and Excess Soil Management, which delays the first phase of provisions were set to come into force. The first phase provisions and consequential amendments to existing regulations are now scheduled to come into force on January 1, 2021. Other implementation dates set out in O. Reg 406/19 remain unchanged.
Insights
-
Litigation and Dispute Resolution
Climate Change Suits Against the Government: Mathur v. Ontario Appeal Decision
The Court of Appeal for Ontario has released its appeal decision in Mathur v. Ontario involving a lawsuit by youth applicants challenging as inadequate Ontario’s legislated targets and plans for… -
Litigation and Dispute Resolution
Director Duties and Climate Change
Decisions earlier this year from the English courts in ClientEarth v Shell Plc et al., and the recent appeal decision from the Court of Appeal of England and Wales, shed light on climate change issues… -
Environmental
Supreme Court of Canada Holds Designated Projects Scheme Under the Impact Assessment Act is Unconstitutional
On October 13, 2023, the Supreme Court of Canada (SCC) released its advisory decision regarding the constitutionality of the federal government’s environmental assessment (EA) regime in Reference re… -
Litigation and Dispute Resolution
Downstream GHG Emissions and Sierra Club Canada Foundation v Canada (Environment and Climate Change)
The Federal Court’s recent decision in Sierra Club Canada Foundation v. Canada (Environment and Climate Change) highlights the continuing focus in Canada on climate change litigation. The case… -
Environmental
Ontario Amends the Mining Act to Streamline Closure Planning and Mineral Recovery Requirements
On May 18, 2023, the Province of Ontario granted Royal Assent to various amendments to the Mining Act through Bill 71, the Building More Mines Act, 2023 (“Bill 71”). The government’s stated purpose of… -
Litigation and Dispute Resolution
Limits of Climate Change Suits Against the Government: Mathur v. Ontario Decision
The Superior Court of Justice has now released its decision in Mathur v. Ontario, a case we wrote about earlier this year and which is now a further example of an unsuccessful claim against a…
Featured Work
-
Mining
Newmont Corporation to sell Musselwhite Gold Mine to Orla Mining for $850 million
Goodmans LLP is advising Newmont Corporation in its agreement to sell the Musselwhite Gold Mine to Orla Mining for $850 million… -
Mining
Newmont Corporation to sell its Éléonore operation to Dhilmar Ltd for $795 million
Goodmans LLP is advising Newmont Corporation in its agreement to sell its Éléonore operation to Dhilmar Ltd for $795 million in cash consideration… -
Mergers and Acquisitions
Group led by Michael Andlauer buys Ottawa Senators
Goodmans LLP acted for an entity controlled by Michael Andlauer in its purchase of the Ottawa Senators Hockey Club from the Melnyk Estate… -
Mergers and Acquisitions
Neighbourly Announces Successful Closing of Take-Private Transaction with Persistence Capital Partners
Goodmans LLP advised Brookfield Asset Management Ltd., through its Special Investments program, in connection with its structured equity investment of $320 million to partially fund the take-private… -
Mergers and Acquisitions
Forum Energy Technologies acquires Variperm Energy Services
Goodmans LLP advised Forum Energy Technologies, Inc. in the acquisition of Variperm Energy Services… -
Mergers and Acquisitions
Cox Enterprises, Inc. disposes Manheim Canada business to OPENLANE for C$130 million
Goodmans LLP advised Cox Enterprises, Inc. in the disposition of Cox Automotive’s Manheim Canada business to OPENLANE for C$130 million…
News & Events
-
Banking and Financial Services
Goodmans Recognized in the Inaugural Edition of Best Law Firms - Canada 2025
Goodmans is delighted to share we are featured in the inaugural edition of Best Law Firms - Canada 2025, recognizing us as one of the country’s exceptional law firms across 40 industries and practices… -
Mergers and Acquisitions
Chambers and Partners Once Again Honours Goodmans with Top-Tier Recognition
We are delighted to announce Goodmans LLP continues to receive top-tier recognition from Chambers and Partners in the Chambers Canada 2025 Guide.Recognition from Chambers and Partners is based on… -
Banking and Financial Services
The Canadian Legal Lexpert Directory 2024 Continues to Recognize Goodmans
We are proud to announce Goodmans LLP has once again been recognized in the 2024 edition of The Canadian Legal Lexpert Directory.91 Goodmans lawyers have been recognized as top-tier in their…