Adjudication under the Construction Act: Tight Timelines and Document Management
The Construction Lien Amendment Act was passed in December 2017 and substantively changed the Construction Lien Act, now the Construction Act (the “Act ”). Its primary purposes were to: (i) modernize the existing Construction Lien Act; (ii) provide prompt payment legislation throughout Ontario; and (iii) introduce adjudication provisions for disputes arising in the course of a contract. For further information on the Construction Act see our June 20, 2018 Update, Construction Act: Here We Go!, as well as our December 17, 2018 Update, Bill 57 and Amendments to the Construction Act.
Adjudication
One of the most significant changes introduced in the Act is an adjudication regime to resolve disputes on construction projects as they arise in the course of the project, rather than at the end of a project.
Unlike typical litigation, or even arbitration, which usually are “after the fact” processes requiring parties to recreate the history, the new adjudication process is intended to achieve real time resolution of construction disputes at unprecedented speed. Therefore, members of Ontario’s construction industry, including owners, contractors and subcontractors, need to ensure they are well positioned to initiate and respond to claims under the tight timelines set out in the Act.
Which Contracts Are Subject to Adjudication?
Although certain provisions of the Act came into force in July 2018, the adjudication provisions will not come into effect until October 1, 2019. Importantly, even then, the adjudication provisions will only apply to construction contracts and subcontracts entered into on or after October 1, 2019.
What Types of Disputes are Subject to Adjudication?
Pursuant to section 13.5(1) of the Act, parties will be able to adjudicate disputes relating to:
i. the valuation of services or materials provided under the contract or subcontract;
ii. payment under the contract or subcontract, including under approved, unapproved, and proposed change orders;
iii. disputes that are the subject of a notice of non-payment under the new prompt payment regime;
iv. amounts retained as set-off;
v. non-payment of holdback; and
vi. any other matter the parties to adjudication agree to.
Unless the adjudicator and the parties agree otherwise, only one “issue” at a time can be referred to adjudication.
Furthermore, unless agreed by the parties, an adjudication may not be commenced after the date the contract or subcontract is completed (section13.5(3)).
Who Can Refer a Dispute to Adjudication?
Either party to a contract may refer a dispute to adjudication. Therefore, while an owner can adjudicate a dispute with a contractor, an owner cannot adjudicate a dispute with a subcontractor.
How is Adjudication Commenced?
Pursuant to section 13.7 of the Act, a party commences the adjudication process by giving the other party written notice of adjudication that includes:
i. the names and addresses of the parties;
ii. the nature and a brief description of the dispute, including details respecting how and when it arose;
iii. the nature of the redress sought; and
iv. the name of a proposed adjudicator to conduct the adjudication.
What Timelines Apply to Adjudication?
Unlike typical litigation, where parties have months to gather documents, and thereafter complete discoveries, the adjudication process is intended to be completed from start to finish in 46 days. Therefore, a party who is organized and able to quickly assemble relevant documents will be at a considerable advantage to initiate and respond to claims.
Once a party has provided a written notice of adjudication, the parties have four days to agree on an adjudicator, failing which one will be chosen by the Authorized Nominating Authority (section 13.9).
Pursuant to section 13.11 of the Act, within five days of the adjudicator being accepted or appointed, the referring party must provide the adjudicator with: (i) the written notice of adjudication; (ii) a copy of the contract or subcontract; and (iii) any documents they intend to rely on. Although there is no timeline specified for when the responding party must provide its own materials, once the adjudicator receives the referring party’s materials, the adjudicator must release its decision within 30 days (section 13.13(1)). Therefore, the responding party will necessarily be required to respond well within that 30-day limit. This poses a potential disadvantage to the responding party. However, the adjudicator can request up to 14 additional days to provide its decision, but this request can be rejected by either party (section 13.13(2)).
Furthermore, although the parties can agree to further time extensions, any such request is subject to the adjudicator’s consent (section 13.13(2)).
Once the adjudicator has made its decision, if payment is ordered, it must be made within 10 days (section 13.19(2)).
What is the Procedure for Adjudication?
The Act allows parties to agree to an adjudication procedure in their contract. If the parties fail to do so, then the procedures under the Act govern (section 13.6).
The Act provides little specific guidance on how the adjudication should be conducted. Instead, the adjudicator is given wide discretion to “conduct the adjudication in the manner he or she determines appropriate in the circumstances” (section 13.12(4)).
Furthermore, pursuant to section 13.12 of the Act, the adjudicator has the power to issue directions respecting the conduct of the adjudication, including the power to:
i. take the initiative in ascertaining the relevant facts and law;
ii. draw inferences based on the parties’ conduct;
iii. conduct onsite inspections of the improvement (subject to the owner’s consent); and
iv. obtain the assistance of an expert (with the adjudicator able to order that one or both parties pay the expert’s fees).
Who Pays for Adjudication?
The parties to the adjudication will each be responsible for an equal share of the adjudicator’s fees (section 13.10(3)). Furthermore, unlike traditional litigation, where the unsuccessful party is often responsible for a portion of the other side’s legal costs, each party to an adjudication will be responsible for their own costs, regardless of the outcome (section 13.16). However, an adjudicator has discretion to order a party to pay all or a portion of the other party’s costs where the party acted in a manner that was “frivolous, vexatious, an abuse of process or other than in good faith” (section 13.17).
How Are Adjudication Decisions Enforced?
Once the adjudicator has rendered its decision, either party may file the determination with the court. The decision is then enforceable as if it were a court Order, including by way of a writ of execution and garnishment (section 13.20).
Perhaps more importantly, in the event a party fails to make the payment ordered by the adjudicator, the unpaid party is entitled to suspend its work on the project. The party in default is then not only responsible to pay the amounts ordered by the adjudicator, plus interest, but they are also responsible to pay the costs of the suspension and any remobilization costs (section13.19).
Can an Adjudicator’s Decision be Appealed?
An adjudicator’s decision cannot be appealed in the traditional sense; however, the decision is an interim decision and therefore the parties are still able to bring the matter before the court or to arbitration once the project is complete. However, the adjudicator’s decision remains binding on the parties throughout the project until a determination is made by the court or an arbitrator, or until the parties agree otherwise (section 13.15).
In addition, either party to the adjudication can bring an application for judicial review to set aside the adjudicator’s decision. Under the Act, to seek judicial review, a party must first bring a motion for leave within 30 days of the adjudicator’s decision (section 13.18). The adjudicator’s decision may be set aside based on one of the following grounds:
i. at the time of the adjudication, one party was operating under a legal incapacity;
ii. the contract between the parties was invalid or ceased to exist;
iii. the determination dealt with a matter that could not be adjudicated, or was unrelated to the subject of the adjudication;
iv. the adjudication was conducted by someone not qualified to be an adjudicator;
v. the procedure for the adjudication did not comply with the procedures set out in the Act;
vi. there was a reasonable apprehension of bias on the adjudicator’s part; or
vii. the adjudicator’s decision was made as a result of fraud (section13.18(5)).
Based on these enumerated grounds, it appears that whether the adjudicator got the decision “right” or “wrong” is not a basis for judicial review. These grounds reflect the fact that an adjudicator must make its decision under tight timelines and that the goal of adjudication is a speedy resolution, even if that means sacrificing “correctness”.
How Can You Prepare for the New Adjudication Regime?
Although the new adjudication regime is still several months away, owners, contractors and subcontractors should start positioning themselves for success. With adjudication’s focus on speed, parties need to ensure their document management systems are accurate, organized, and current, and that documents are easily accessible. A party who can quickly pull together the relevant documents to bring or respond to a claim will have an immediate advantage; forewarned is forearmed!
The Act gives considerable leeway to the parties to specify in their contract agreement the adjudication procedures to be followed. Owners, contractors and subcontractors should begin considering what type of procedure best suits their interests, and ensure these procedures are clearly set forth in their contracts. Notably, parties are prohibited from contracting out of the Act.
Expertise
Authors
Insights
-
Environmental
Supreme Court of Canada Holds Designated Projects Scheme Under the Impact Assessment Act is Unconstitutional
On October 13, 2023, the Supreme Court of Canada (SCC) released its advisory decision regarding the constitutionality of the federal government’s environmental assessment (EA) regime in Reference re… -
Cleantech
Government of Canada Publishes Revised Proposal for Greenhouse Gas Offset System
On July 2, 2020, the federal government published a discussion paper entitled Carbon Pollution Pricing: Considerations for Protocol Development in the Federal Greenhouse Offset System (the “Proposal… -
Environmental
Ontario Postpones Commencement of Excess Soil Regulation
The Province of Ontario recently announced that the implementation of the new Excess Soil Regulation, O. Reg 406/19: On-Site and Excess Soil Management (O. Reg 406/19), would be delayed as a result of… -
Construction and Infrastructure
COVID-19: Further Developments in Ontario Construction Law
An overview of two significant developments regarding limitation periods and procedural time periods, and the expansion construction projects considered "essential… -
Construction and Infrastructure
COVID-19 - Ontario Construction Law Update
The COVID-19 pandemic has affected industries across the globe, and the construction industry is no exception. This update addresses recent events that have impacted the construction industry in… -
Construction and Infrastructure
Construction, Builders' and Mechanics' Liens in Canada, 8th Edition
Howard Wise, is a co-author of Construction, Builders’ and Mechanics’ Liens in Canada, 8th Edition.Ontario’s Construction regime has gone through several significant changes, beginning in July…
Featured Work
-
Capital Markets
Brookfield Infrastructure $700 million Medium-Term Note Offering
Goodmans LLP acted for the syndicate of agents led by TD Securities Inc., on the sale by Brookfield Infrastructure of $700 million aggregate principal amount of medium-term notes… -
Real Estate
Harrison Street leads various real estate acquisitions
Goodmans LLP represented Harrison Street, a leading investment management firm headquartered in Chicago and exclusively focused on alternative real assets, on various real estate acquisitions in… -
Construction and Infrastructure
HB Construction Co. v. Potash Corp. of Saskatchewan Inc. et al
Goodmans LLP acted for HB Construction Co. in respect of the construction of a mine in New Brunswick. The litigation relates to a claim in respect of the installation of mechanical and electrical… -
Construction and Infrastructure
North America Construction's Dispute with Utilities Kingdom
Goodmans LLP is acting for North America Construction (“NAC”) in its lawsuit against Utilities Kingdom where NAC claims Utilities Kingston owes it and its workers $29 million after its contract was… -
Real Estate
RioCan REIT, Allied Properties REIT and Diamondcorp Acquisition and Subsequent Redevelopment of 'The Well'
Goodmans LLP acted as counsel for RioCan REIT, Allied Properties REIT and Diamondcorp in connection with acquisition and development of “The Well” mixed use commercial/residential development and in… -
Real Estate
Canada Mortgage and Housing Corporation’s $400 Million Financing
Goodmans LLP acted for Canada Mortgage and Housing Corporation (“CMHC”), in connection with CMHC’s Rental Construction Financing Initiative (“RCFi”), providing first mortgage construction financing to…
News & Events
-
Construction and Infrastructure
Goodmans Recognized in the Lexpert Special Edition: Infrastructure 2024
We are delighted to announce that the Lexpert Special Edition: Infrastructure 2024 has once again recognized Goodmans LLP lawyers among Canada's experts in the infrastructure… -
Banking and Financial Services
The Canadian Legal Lexpert Directory 2024 Continues to Recognize Goodmans
We are proud to announce Goodmans LLP has once again been recognized in the 2024 edition of The Canadian Legal Lexpert Directory.91 Goodmans lawyers have been recognized as top-tier in their… -
Banking and Financial Services
Who's Who Legal Continues to Recognize Goodmans in the Canada 2023 Guide
We are pleased to share Goodmans lawyers have been recognized across Who's Who Legal's National Guide: Canada 2023. WWL National Guides identify national or regional leaders in a sector, industry…